Industrial Bund Demolition

Case Study

Case Study: Industrial Bund Demolition

In Case Studies


Customer Overview

  • Plastic Moulding Company, South Wales
  • Site contained bunded area for the storage of bulk styrene based resin and organic peroxide hardeners
  • Permitted site by Environment Agency and client

Requirements

  • Clear bunded area
  • Decontaminate bunded area
  • Produce samples and analysis of contaminated and surrounding soil areas for submission to the Environment Agency

Features

  • Complete Project Management and contractor liaison
  • Health and Safety management
  • Bore hole testing
  • Ground sampling and classification
  • Disposal of waste items
  • Minimum disruption to continued operations in other areas of the site

Benefits

  • Effective separation of hazardous and non-hazardous wastes sent for disposal and treatment
  • A comprehensive report submitted to the Environment Agency
  • Project completion to client’s approval
  • Full traceability
  • Works completed on time